Week 4: Optimization and Reliability
Schedule constraint: Mon/Wed/Thu 2:30–6:00 pm (~10.5 hrs).
Goals
- 30-minute burn-in pass with temps logged; no brownouts.
- Cycle time improved 10% vs Week 3 baseline.
- L3 tested (if chosen) and documented; otherwise L2 locked.
- Inspection checklist completed (bumper gap, PD/radio, consent, load-in).
- Re-weigh plan documented.
- Burn-in report template completed (temps/currents over time).
- Pre-inspection photo set checklist completed.
Plan & time budget (ETA ~10.5 hrs, Thu as buffer)
- 2.0h: Burn-in (30 min) with telemetry capture; review temps/voltage.
- 1.5h: Cycle-time tuning; run timed drills to shave 10%.
- 1.5h: Climb L3 test (if applicable) or finalize L2; log results.
- 1.0h: Inspection checklist run; fix findings; document re-weigh plan.
- 1.0h: Debrief and doc updates.
Checklist
- 30-minute burn-in with temps logged
- Cycle time improved 10% vs Week 3
- L3 attempt tested (if applicable) and documented
- Inspection checklist completed (bumper gap, PD/radio, consent, load-in)
- Re-weigh plan documented
- Burn-in report saved
- Pre-inspection photo set captured
- Risks/dependencies updated
Owners
- Reliability Lead: burn-in, inspection checklist
- Mech Lead: climb finalize
- Drive Coach: cycle-time drills
- Electrical Lead: monitor temps/voltage
Risks and mitigations
- Risk: Overheating. Mitigation: add fans, detune acceleration, swap gearing.
- Risk: Inspection fail. Mitigation: rerun checklist nightly; rebuild bumpers if needed.
Priorities (P0 must, P1 should, P2 stretch)
- P0: 30-min burn-in pass; cycle time +10% improvement; inspection checklist done; re-weigh plan.
- P1: L3 test documented (or L2 locked); burn-in report saved; pre-inspection photos.
- P2: Extra optimization passes if time remains.
Time tracking tips
- Log burn-in start/end and ambient temp; review data immediately after.
- Track cycle-time drill durations; compare against Week 3 baseline.
Tips for students
- Label any changes made during burn-in so you can revert if needed.
- Keep inspection photos organized (angles/labels) in a shared folder.
Tips for mentors
- Watch for subtle brownouts; adjust current/ramp limits if needed.
- Use a checklist during burn-in to note any rattles/loose hardware for quick fixes.